Construction Status Information

Winter 2011-2012

Between North Valley Road and the Valley Creek

  • Complete clearing, right-of-way fencing northbound

  • Begin construction of sound wall post foundations

  • Northbound traffic shifted to southbound side

  • Begin excavation of old northbound lanes

  • Begin excavation in shoulder area for new third lane and northbound construction of collector-distributor lane

  • Begin northbound drainage installation

Latest Press Releases