U.S. Route 202 - Section 300 in Chester County
Construction Status

July 2010

At Route 401/Conestoga Road and Phoenixville Pike

  • Intersection Improvements Completed

At Phoenixville Pike/Planebrook Road and Swedesford Road

  • Intersection Improvements Completed

Swedesford Road Bridge, between Church Road and Phoenixville Pike

  • Bridge Completed in November 2008

Mill Lane Bridge

  • Bridge Reopened in December 2007

Church Road Bridge

  • Bridge Reopened in November 2008.

Route 29/Morehall Road Bridge

  • Bridge Completed in July 2010.

Swedesford Road Bridge, at PA 29 Interchange

  • New bridge Completed in June 2010.

Cedar Hollow Road Bridge

  • New bridge Completed and opened in December 2008

Railroad Overpass

  • Bridge has been raised to provide increased vertical clearance. Repainting will be done during construction to widen Route 202. 